CUP: J69E04000070002
(DB0800_PAR-FAS_2008_CSP106) COSTRUZIONE DELLA NUOVA STAZIONE DI SOLLEVAMENTO DORA IN SPONDA SINISTRA DEL FIUME DORA BALTEA IN COMUNE DI VILLAREGGIA, DISGIUNTA DALL
SUMMARY OF THE PROJECT
(DB0800_PAR-FAS_2008_CSP106) COSTRUZIONE DELLA NUOVA STAZIONE DI SOLLEVAMENTO DORA IN SPONDA SINISTRA DEL FIUME DORA BALTEA IN COMUNE DI VILLAREGGIA, DISGIUNTA DALL
Implementation indicator
Capacità della rete idrica oggetto di intervento
- Target
- 5 mc/s
- Achieved
- 5 mc/s
Download project
Funding monitored
€ 9,216,993.97
of which cohesion funds
€ 7,789,554.30
Given name | Amount |
---|---|
Development and Cohesion Fund | 7789554.30 |
Another public source | 1427439.67 |
Payments monitored
€ 8,516,708.13
of which cohesion funds
€ 7,789,554.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 1482326.28 | 1482326.28 | 16 |
2010 | 2188291.20 | 3670617.48 | 39 |
2011 | 2748621.29 | 6419238.77 | 69 |
2012 | 1767357.78 | 8186596.55 | 88 |
2013 | 1367.01 | 8187963.56 | 88 |
2014 | 31040.68 | 8219004.24 | 89 |
2015 | 1140.00 | 8220144.24 | 89 |
2016 | 0 | 8220144.24 | 89 |
2017 | 296563.89 | 8516708.13 | 92 |
State of progress
Open
Expected start: 12/11/2008
Effective start: 12/11/2008
Expected end: 28/02/2012
Effective end: 31/01/2012
Entities
- Planning body
- A11000 DIREZIONE RISORSE FINANZIARIE E PATRIMONIO
- Implementing body
- COUTENZA CANALI CAVOUR
- Beneficiary
- COUTENZA CANALI CAVOUR
- Executor
- COUTENZA CANALI CAVOUR
Programming area
- Programme
- PSC PIEDMONT
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 7,789,554.30
- Payments on cohesion funds
- € 7,789,554.30
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche