CUP: I97H14001230002
(A11_2014_190-2014_63) INTERVENTI URGENTI A SEGUITO ALLUVIONE AUTUNNO 2014 - O.S. 40-42-44. DA 48 A 52, 54 - SISTEMAZIONE RETE VIARIA
Download project
Funding monitored
€ 76,810.00
of which cohesion funds
€ 0.00
Given name | Amount |
---|---|
Another public source | 76810.00 |
Payments monitored
€ 76,810.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 76810.00 | 76810.00 | 100 |
State of progress
Completed
Expected start: 26/11/2014
Effective start: 26/11/2014
Expected end: 16/02/2015
Effective end: 16/02/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Environment
- Prevenzione dei rischi (inclusa elaborazione e attuazione di piani e provvedimenti))
Territory
Entities
- Planning body
- A11000 DIREZIONE RISORSE FINANZIARIE E PATRIMONIO
- Implementing body
- COMUNE DI GAVI
- Beneficiary
- COMUNE DI GAVI
- Executor
- COMUNE DI GAVI
- Priority QSN
- Reti e collegamenti per la mobilità
- General objective QSN
- Accelerare la realizzazione di un sistema di trasporto efficiente, integrato, flessibile,sicuro e sostenibile per assicurare servizi logistici e di trasporto funzionali allo sviluppo
- Specific objective QSN
- Favorire la connessione delle aree produttive e dei sistemi urbani alle reti principali, le sinergie tra i territori e i nodi logistici e l'accessibilità delle aree periferiche: migliorare i servizi di trasporto a livello regionale e promuovere modalità sostenibili
Programming area
- Programme
- PAR FSC PIEMONTE
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 0.00
- Payments on cohesion funds
- € 0.00
- Line
- Sistema fluviale del PO e reti idriche
- Action
- Interventi di difesa del suolo