CUP: G47E12000130002
(DB0800_PAR-FAS_2012_MAIRA) NODO IDRAULICO DI SAVIGLIANO COMPLETAMENTO OPERE DI ARGINATURA TORRENTE MAIRA
SUMMARY OF THE PROJECT
(DB0800_PAR-FAS_2012_MAIRA) NODO IDRAULICO DI SAVIGLIANO COMPLETAMENTO OPERE DI ARGINATURA TORRENTE MAIRA
Implementation indicator
Estensione della rete
- Target
- 2.15 km
- Achieved
- 2.15 km
Download project
Funding monitored
€ 2,682,831.69
of which cohesion funds
€ 2,201,890.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 2583865.00 |
Region | 98966.69 |
- Economies:
- € 17,168.31
Payments monitored
€ 2,300,857.67
of which cohesion funds
€ 2,201,890.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2008 | 11681.24 | 11681.24 | 0 |
2009 | 1967.95 | 13649.19 | 0 |
2010 | 4845.75 | 18494.94 | 0 |
2011 | 36650.33 | 55145.27 | 2 |
2012 | 0 | 55145.27 | 2 |
2013 | 533.01 | 55678.28 | 2 |
2014 | 24719.49 | 80397.77 | 2 |
2015 | 428763.04 | 509160.81 | 18 |
2016 | 1098281.24 | 1607442.05 | 59 |
2017 | 163560.91 | 1771002.96 | 66 |
2018 | 488382.49 | 2259385.45 | 84 |
2019 | 41472.22 | 2300857.67 | 85 |
State of progress
Open
Expected start: 01/09/2014
Effective start: 15/07/2015
Expected end: 31/12/2015
Effective end: 26/06/2016
Entities
- Planning body
- A11000 DIREZIONE RISORSE FINANZIARIE E PATRIMONIO
- Implementing body
- COMUNE DI SAVIGLIANO
- Beneficiary
- COMUNE DI SAVIGLIANO
- Executor
- COMUNE DI SAVIGLIANO
Programming area
- Programme
- PSC PIEDMONT
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 2,201,890.98
- Payments on cohesion funds
- € 2,201,890.98
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico