CUP: J62C09000120007
(0111000334) IMPIANTO FOTOVOLTAICOSU COPERTURA EDIFICIO SEDE AZIENDALE
Download project
Funding monitored
€ 85,978.97
of which cohesion funds
€ 85,770.20
Given name | Amount |
---|---|
European Union | 34022.84 |
Revolving Fund (National co-financing) | 39971.87 |
Region | 11984.26 |
- Other resources - Private:
- € 13,503
Payments monitored
€ 85,978.97
of which cohesion funds
€ 85,770.20
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 88348.40 | 88348.40 | 102 |
2011 | 0 | 88348.40 | 102 |
2012 | -2369.43 | 85978.97 | 100 |
State of progress
Completed
Expected start: 13/02/2009
Effective start: 03/03/2010
Expected end: 15/01/2012
Effective end: 03/03/2010
Type
- Incentives for firms
- NUOVA REALIZZAZIONE
Theme
- Energy
- Energia rinnovabile: idroelettrica, geotermale e altra
Territory
Entities
- Planning body
- FINPIEMONTE SPA
- Implementing body
- OFFICINA MECCANICA RAIMO DI PAOLETTI SILVIA & STEFANO SNC
- Beneficiary
- OFFICINA MECCANICA RAIMO DI PAOLETTI SILVIA & STEFANO SNC
- Executor
- OFFICINA MECCANICA RAIMO DI PAOLETTI SILVIA & STEFANO SNC
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF PIEDMONT
- Axis
- Sostenibilità ed efficienza energetica
- Operational objective
- Ridurre l'uso intensivo delle fonti energetiche tradizionali attraverso l'incremento della produzione energetica da fonti rinnovabili e promuovere l'efficienza ed il risparmio energetico nella produzione e consumo di energia.