Updated on 31/08/2018
Funding monitored € 316,005.50 of which cohesion funds € 316,005.50
Given name Amount
European Union75026.03
Revolving Fund (National co-financing)88146.57
Region26430.70
Another public source126402.20
Payments monitored € 316,005.50 of which cohesion funds € 316,005.50
Year Amount Cumulative amount Percentage on public financing
20091483.201483.200
201001483.200
2011286293.54287776.7491
201228228.76316005.50100

State of progress

Completed
Expected start: 20/05/2011
Effective start: 20/05/2011
Expected end: 18/08/2011
Effective end: 18/08/2011

Type

Theme

  • Energy
  • Efficienza dell'energia, cogenerazione, gestione dell'energia

Territory

Entities

Planning body
REGIONE PIEMONTE
Implementing body
COMUNE DI BUSCA
Beneficiary
COMUNE DI BUSCA
Executor
COMUNE DI BUSCA
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
Specific objective QSN
Promozione dell'efficienza energetica e del risparmio dell'energia

Programming area

Programme
ROP RCE ERDF PIEDMONT
European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Cohesion funds
€ 316,005.50
Payments on cohesion funds
€ 316,005.50
Axis
Sostenibilità ed efficienza energetica
Operational objective
Ridurre l'uso intensivo delle fonti energetiche tradizionali attraverso l'incremento della produzione energetica da fonti rinnovabili e promuovere l'efficienza ed il risparmio energetico nella produzione e consumo di energia.