Updated on 31/08/2018
Funding monitored € 226,974.58 of which cohesion funds € 226,974.58
Given name Amount
European Union89813.51
Revolving Fund (National co-financing)105528.27
Region31632.80
Other resources - Private:
€ 33,204
Payments monitored € 226,974.58 of which cohesion funds € 226,974.58
Year Amount Cumulative amount Percentage on public financing
2009195135.00195135.0085
201031839.58226974.58100

State of progress

Completed
Expected start: 17/10/2008
Effective start: 17/10/2008
Expected end: 15/07/2011
Effective end: 15/07/2011

Type

Theme

  • Energy
  • Energia rinnovabile: idroelettrica, geotermale e altra

Territory

Entities

Planning body
FINPIEMONTE
Implementing body
SOMOTER SRL
Beneficiary
SOMOTER SRL
Executor
SOMOTER SRL
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
Specific objective QSN
Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili

Programming area

Programme
ROP RCE ERDF PIEDMONT
European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Cohesion funds
€ 226,974.58
Payments on cohesion funds
€ 226,974.58
Axis
Sostenibilità ed efficienza energetica
Operational objective
Ridurre l'uso intensivo delle fonti energetiche tradizionali attraverso l'incremento della produzione energetica da fonti rinnovabili e promuovere l'efficienza ed il risparmio energetico nella produzione e consumo di energia.