CUP: F91C19000010001
(A19_POR-FESR-2014-2020_2019_FD7217) Riqualificazione illuminazione pubblica POR FESR 2014/2020 azione IV4c13
SUMMARY OF THE PROJECT
(A19_POR-FESR-2014-2020_2019_FD7217) Riqualificazione illuminazione pubblica POR FESR 2014/2020 azione IV4c13
Implementation indicator
Punti illuminanti/luce
- Target
- 79 num
- Achieved
- 79 num
Download project
Funding monitored
€ 55,155.71
of which cohesion funds
€ 55,155.71
Given name | Amount |
---|---|
European Union | 21660.42 |
Revolving Fund | 15162.29 |
Region | 6498.12 |
Another public source | 11834.88 |
Payments monitored
€ 54,151.06
of which cohesion funds
€ 54,151.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 1808.04 | 1808.04 | 3 |
2020 | 52343.02 | 54151.06 | 98 |
State of progress
Completed
Expected start: 01/09/2020
Effective start: 24/08/2020
Expected end: 30/11/2020
Effective end: 05/11/2020
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- REGIONE PIEMONTE
- Beneficiary
- COMUNE DI ROASIO
- Executor
-
MECHANIKOI SRL
BIELETTRICA DI SECCO ALBERTO & C SAS
Programming area
- Programme
- ROP ERDF PIEDMONT
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 55,155.71
- Payments on cohesion funds
- € 54,151.06
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili