CUP: J53C17000810009
(030701175C) INSTALLAZIONE IMPIANTO FOTOVOLTAICO
SUMMARY OF THE PROJECT
(030701175C) INSTALLAZIONE IMPIANTO FOTOVOLTAICO
Implementation indicators
Numero di imprese che ricevono un sostegno
- Target
- 1 num
- Achieved
- 1 num
Numero di imprese che ricevono sovvenzioni (a fondo perduto)
- Target
- 1 num
- Achieved
- 1 num
Diminuzione annuale stimata dei gas a effetto serra
- Target
- 565 teq
- Achieved
- 565 teq
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 232,000.00
of which cohesion funds
€ 232,000.00
Given name | Amount |
---|---|
European Union | 116000.00 |
Revolving Fund | 81200.00 |
Region | 34800.00 |
- Other resources - Private:
- € 928,000
Payments monitored
€ 232,000.00
of which cohesion funds
€ 232,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 232000.00 | 232000.00 | 100 |
State of progress
Settled
Expected start: 07/08/2017
Effective start: 07/08/2017
Expected end: 31/12/2020
Effective end: not available
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- FINPIEMONTE
- Beneficiary
- ILTAR-ITALBOX INDUSTRIE RIUNITE - SPA
- Executor
- ILTAR-ITALBOX INDUSTRIE RIUNITE - SPA
Programming area
- Programme
- ROP ERDF PIEDMONT
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 232,000.00
- Payments on cohesion funds
- € 232,000.00
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici e delle emissioni nelle imprese e integrazione di fonti rinnovabili