CUP: G86J18000180002
(A19_POR FESR 2014-2020_2017_FD2941) Rifacimento centrale termica, rete di distribuzione e riqualificazione di edifici comunali
SUMMARY OF THE PROJECT
(A19_POR FESR 2014-2020_2017_FD2941) Rifacimento centrale termica, rete di distribuzione e riqualificazione di edifici comunali
Download project
Funding monitored
€ 443,609.68
of which cohesion funds
€ 443,609.68
Given name | Amount |
---|---|
European Union | 177443.87 |
Revolving Fund | 124210.71 |
Region | 53233.16 |
Another public source | 88721.94 |
Payments monitored
€ 441,593.27
of which cohesion funds
€ 441,593.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 12053.60 | 12053.60 | 2 |
2019 | 339459.64 | 351513.24 | 79 |
2020 | 90080.03 | 441593.27 | 99 |
State of progress
Completed
Expected start: 06/05/2019
Effective start: 06/05/2019
Expected end: 31/12/2020
Effective end: 08/06/2020
Entities
- Planning body
- REGIONE PIEMONTE
- Implementing body
- REGIONE PIEMONTE
- Beneficiary
- COMUNE DI FRASSINETTO
- Executor
-
TRUFFA IMPIANTI SRL
SPE STUDIO PROGETTO ENERGIA DIVISIONE CLIMA
Programming area
- Programme
- ROP ERDF PIEDMONT
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 443,609.68
- Payments on cohesion funds
- € 441,593.27
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
Efficientamento energetico di VIA ROMA | € 164,151 |
Same type of investment
(A21_2022_FRASSINETTO) Il Borgo e il Pittore borgata Capelli e Carlo Bonatto Minella | € 1,380,000 |