CUP: F78E17000050005
LAVORI DI CONSOLIDAMENTO STRUTTURALE DEL FABBRICATO ¿COMPRENSIVO ROSETTI¿
SUMMARY OF THE PROJECT
IL COMPRENSIVO ROSETTI E' COMPOSTO DA DUE EDIFICI, 1 DEL 2013 L'ALTRO DEL 1972. SU QUEST0ULTIMO SARA' ESEGUITO UN INTERVENTO DI CONSOLIDAMENTO STRUTTURALE CON MIGLIORAMENTO SISMICO AL 60% IN 2 STRALCI. IL PRIMO STRALCIO HA UN COTO DI ¬ 800.000
Implementation indicator
Interventi per la messa in sicurezza degli edifici scolastici
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 798,440.06
of which cohesion funds
€ 798,440.06
Given name | Amount |
---|---|
Development and Cohesion Fund | 798440.06 |
- Economies:
- € 1,559.94
Payments monitored
€ 798,440.06
of which cohesion funds
€ 798,440.06
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 8374.08 | 8374.08 | 1 |
2019 | 618139.60 | 626513.68 | 78 |
2020 | 170298.38 | 796812.06 | 99 |
2021 | 1628.00 | 798440.06 | 100 |
State of progress
Completed
Expected start: 02/05/2019
Effective start: 02/05/2019
Expected end: 30/08/2019
Effective end: 26/02/2020
Entities
- Planning body
- COMUNE DI FORLIMPOPOLI
- Implementing body
- COMUNE DI FORLIMPOPOLI
- Beneficiary
- COMUNE DI FORLIMPOPOLI
- Executor
- CEIR SOC CONS COOP
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- RISORSE FSC ASSEGNATE AI COMUNI
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture pubbliche, didattiche/universitarie, sociali e sanitarie