CUP: C65F10000200008
IMPIANTO FOTOVOLTAICO
Funding monitored
€ 156,253.24
of which cohesion funds
€ 156,253.24
Given name | Amount |
---|---|
European Union | 46875.97 |
Revolving Fund (National co-financing) | 62501.30 |
Region | 46875.97 |
- Economies:
- € 5,940.40
- Other resources - Private:
- € 676,966
Payments monitored
€ 156,253.24
of which cohesion funds
€ 156,253.24
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 156253.24 | 156253.24 | 100 |
State of progress
Completed
Expected start: 28/10/2010
Effective start: 26/08/2010
Expected end: 28/10/2011
Effective end: 10/08/2011
Entities
- Planning body
- PROVINCIA AUTONOMA DI TRENTO
- Implementing body
- FERRARI F.LLI LUNELLI SPA
- Beneficiary
- FERRARI F.LLI LUNELLI SPA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF PA TRENTO
- Axis
- ENERGIA/AMBIENTE E DISTRETTO TECNOLOGICO
- Operational objective
- Promuovere la sostenibilità nel campo dell'edilizia e della gestione del territorio.
Other projects in territory
Same theme
Same type of investment
IMPIANTO FOTOVOLTAICO | € 168,269 |
I - COGENERAZIONE | € 163,041 |
IMPIANTO FOTOVOLTAICO | € 155,104 |
IMPIANTO FOTOVOLTAICO | € 129,974 |
IMPIANTO FOTOVOLTAICO | € 121,531 |