CUP: C54E14000320008
C - IMPIANTI FOTOVOLTAICI
Download project
Funding monitored
€ 5,703.60
of which cohesion funds
€ 5,703.60
Given name | Amount |
---|---|
European Union | 1711.08 |
Revolving Fund (National co-financing) | 2281.44 |
Region | 1711.08 |
- Economies:
- € 206.40
- Other resources - Private:
- € 14,560
Payments monitored
€ 5,703.60
of which cohesion funds
€ 5,703.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 5703.60 | 5703.60 | 100 |
State of progress
Completed
Expected start: 25/06/2014
Effective start: 04/05/2015
Expected end: 05/11/2015
Effective end: 22/06/2015
Entities
- Planning body
- PROVINCIA AUTONOMA DI TRENTO
- Implementing body
- TAURIS DI PERINI FALIERO & C. SAS
- Beneficiary
- TAURIS DI PERINI FALIERO & C. SAS
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF PA TRENTO
- Axis
- ENERGIA/AMBIENTE E DISTRETTO TECNOLOGICO
- Operational objective
- Promuovere la sostenibilità nel campo dell'edilizia e della gestione del territorio.
Other projects in territory
Same theme
IMPIANTO FOTOVOLTAICO | € 158,353 |
LAVORI DI ADEGUAMENTO TECNOLOGICO DEGLI IMPIANTI DI PUBBLICA ILLUMINAZIONE NEL COMUNE DI ARCO VIA GAZZOLETTI E VIA NARZELLE | € 84,769 |
C - IMPIANTI FOTOVOLTAICI | € 5,919 |
Same type of investment
IMPIANTO FOTOVOLTAICO | € 158,353 |
C - IMPIANTI FOTOVOLTAICI | € 5,919 |