CUP: D84E12001190006
EFFICIENTAMENTO ENERGETICO EDIFICI PUBBLICI
Download project
Funding monitored
€ 254,735.26
of which cohesion funds
€ 254,735.26
Given name | Amount |
---|---|
Revolving Fund (Cohesion Action Plan) | 254735.26 |
Payments monitored
€ 244,718.76
of which cohesion funds
€ 244,718.76
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 84571.17 | 84571.17 | 33 |
2016 | 96946.70 | 181517.87 | 71 |
2017 | 0 | 181517.87 | 71 |
2018 | 0 | 181517.87 | 71 |
2019 | 63200.89 | 244718.76 | 96 |
State of progress
Settled
Expected start: 31/10/2015
Effective start: 31/10/2015
Expected end: 30/06/2016
Effective end: not available
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI BARANELLO
- Beneficiary
- COMUNE DI BARANELLO
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- 2007-2013 Cohesion Action Plan
- 2007-2013 Cohesion Action Plan
- Programme
- PROGRAMMA PAC MOLISE
- Line
- Salvaguardia
- Action
- PISU
Other projects in territory
Same theme
INTERVENTI DI RISPARMIO ED EFFICIENZA ENERGETICA - COMUNE DI BARANELLO | € 183,008 |