CUP: G61E15000680007
PROGETTO FINALIZZATO A RENDERE ENERGETICAMENTE PIù EFFICIENTI GLI UTILIZZI DEGLI EDIFICI PUBBLICI E LE UTENZE ENERGETICHE PUBBLICHE
Download project
Funding monitored
€ 184,219.28
of which cohesion funds
€ 167,464.65
Given name | Amount |
---|---|
European Union | 167464.65 |
Development and Cohesion Fund | 16754.63 |
Payments monitored
€ 184,219.28
of which cohesion funds
€ 167,464.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 167464.65 | 167464.65 | 90 |
2016 | 16754.63 | 184219.28 | 100 |
State of progress
Completed
Expected start: 26/11/2015
Effective start: 26/11/2015
Expected end: 12/12/2015
Effective end: 12/12/2015
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE MOLISE
- Implementing body
- COMUNE DI CHIAUCI
- Beneficiary
- COMUNE DI CHIAUCI
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Promozione dell'efficienza energetica e del risparmio dell'energia
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF MOLISE
- Axis
- Energia
- Operational objective
- Sostenere e promuovere l'efficienza energetica, la diffusione di processi a minore domanda energetica e la valorizzazione di fonti energetiche rinnovabili.
Other projects in territory
Same theme
INSTALLAZIONE IMPIANTO FOTOVOLTAICO SULL'EX EDIFICIO SCOLASTICO ED EFFICIENTAMENTO DEI CORPI ILLUMINANTI INTERNI DELLA SEDE COMUNALE | € 45,981 |