CUP: J89I20000110001
ISTITUTO PENALE CASAL DEL MARMO ROMA - RIFACIMENTO PISTA DI ATLETICA ALL'APERTO DELLO STADIO E ALTRE MIGLIORIE
SUMMARY OF THE PROJECT
RIFACIMENTO PISTA DI ATLETICA ALL'APERTO DELLO STADIO, PISTA INDOOR, RINNOVAMNETO CENTRO FISIOTERAPIA E AMMORDENAMENTO FORESTERIA ATLETI
Implementation indicator
Superficie oggetto di intervento
- Target
- 895,509 mq
- Achieved
- 895,509 mq
Download project
Funding monitored
€ 895,509.00
of which cohesion funds
€ 895,509.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 895509.00 |
Payments monitored
€ 751,198.99
of which cohesion funds
€ 751,198.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 233503.62 | 233503.62 | 26 |
2022 | 421370.40 | 654874.02 | 73 |
2023 | 96324.97 | 751198.99 | 83 |
State of progress
Open
Expected start: 15/02/2021
Effective start: 15/02/2021
Expected end: 25/06/2021
Effective end: 25/06/2021
Entities
- Planning body
- POLIZIA PENITENZIARIA
- Beneficiary
- POLIZIA PENITENZIARIA
Programming area
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Programme
- IMPIANTI SPORTIVI PER GRUPPI SPORTIVI MILITARI
- Line
- Infrastrutture
- Action
- Infrastrutture pubbliche, didattiche/universitarie, sociali e sanitarie