CUP: G24H15001760009
PIGNA MARE - FORNITURA E POSA IN OPERA DI NUOVA TECNOLOGIA ADEGUAMENTO/SOSTITUZIONE APPARECCHI ILLUMINANTI ESISTENTI A LED IN SANREMO CENTRO STORICO
Download project
Funding monitored
€ 407,861.94
of which cohesion funds
€ 407,861.94
Given name | Amount |
---|---|
European Union | 123990.03 |
Revolving Fund (National co-financing) | 120727.13 |
Region | 81572.39 |
Municipality | 81572.39 |
Payments monitored
€ 407,861.94
of which cohesion funds
€ 407,861.94
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 409610.58 | 409610.58 | 100 |
2016 | -1748.64 | 407861.94 | 100 |
State of progress
Completed
Expected start: 20/05/2015
Effective start: 20/05/2015
Expected end: 31/12/2015
Effective end: 25/05/2015
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Progetti integrati per la rigenerazione urbana e rurale
Territory
Entities
- Planning body
- REGIONE LIGURIA
- Implementing body
- COMUNE DI SANREMO
- Priority QSN
- Competitività e attrattività delle città e dei sistemi urbani
- General objective QSN
- Promuovere la competitività, l'innovazione e l'attrattività delle città e delle reti urbane attraverso la diffusione di servizi avanzati di qualità, il miglioramento della qualità della vita, e il collegamento con le reti materiali e immateriali
- Specific objective QSN
- Sostenere la crescita e la diffusione delle funzioni urbane superiori per aumentare la competitività e per migliorare la fornitura di servizi di qualità nelle città e nei bacini territoriali sovracomunali e regionali di riferimento
Programming area
- Programme
- ROP RCE ERDF LIGURIA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 407,861.94
- Payments on cohesion funds
- € 407,861.94
- Axis
- SVILUPPO URBANO
- Operational objective
- Sviluppo urbano sostenibile.