CUP: E67H09001020001
COLLETTAMENTO REFLUI DEL DIANESE E ADDUZIONE AL DEPURATORE DI IMPERIA
SUMMARY OF THE PROJECT
COLLETTAMENTO REFLUI DEL DIANESE E ADDUZIONE AL DEPURATORE DI IMPERIA
Implementation indicator
Estensione della rete
- Target
- 4.63 km
- Achieved
- 0 km
Download project
Funding monitored
€ 4,157,382.98
of which cohesion funds
€ 2,024,645.48
Given name | Amount |
---|---|
Development and Cohesion Fund | 2024645.48 |
Another public source | 2132737.50 |
- Economies:
- € 459,752.20
Payments monitored
€ 4,157,382.98
of which cohesion funds
€ 2,024,645.48
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2015 | 6136.22 | 6136.22 | 0 |
2016 | 2393918.61 | 2400054.83 | 57 |
2017 | 1751428.14 | 4151482.97 | 99 |
2018 | 5900.01 | 4157382.98 | 100 |
State of progress
Completed
Expected start: 01/03/2015
Effective start: 29/02/2016
Expected end: 29/02/2016
Effective end: 19/05/2017
Entities
- Planning body
- REGIONE LIGURIA
- Beneficiary
- COMUNE DI DIANO MARINA
Programming area
- Programme
- PSC REGIONE LIGURIA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 2,024,645.48
- Payments on cohesion funds
- € 2,024,645.48
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche