CUP: D37H13001310002
LAVORI DI CONSOLIDAMENTO E RIPRISTINO STRADA COMUNALE PER LA FRAZIONE DI VEZZOLA LATO OVEST
SUMMARY OF THE PROJECT
LAVORI DI CONSOLIDAMENTO E RIPRISTINO STRADA COMUNALE PER LA FRAZIONE DI VEZZOLA LATO OVEST
Implementation indicator
Estensione in lunghezza
- Target
- 0.10 km
- Achieved
- 0.10 km
Download project
Funding monitored
€ 82,181.29
of which cohesion funds
€ 82,181.29
Given name | Amount |
---|---|
Development and Cohesion Fund | 82181.29 |
Payments monitored
€ 82,181.29
of which cohesion funds
€ 82,181.29
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2014 | 72956.00 | 72956.00 | 88 |
2015 | 9225.29 | 82181.29 | 100 |
State of progress
Completed
Expected start: 22/04/2014
Effective start: 22/04/2014
Expected end: 29/09/2014
Effective end: 15/09/2014
Entities
- Planning body
- REGIONE LIGURIA
- Beneficiary
- COMUNE DI ZIGNAGO
Programming area
- Programme
- PSC REGIONE LIGURIA
- 2007-2013 National Development and Cohesion Fund
- 2007-2013 National Development and Cohesion Fund
- Cohesion funds
- € 82,181.29
- Payments on cohesion funds
- € 82,181.29
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
LAVORI DI CONSOLIDAMENTO E RIPRISTINO STRADA COMUNALE PER LA FRAZIONE DI SERO' | € 31,611 |
LAVORI DI CONSOLIDAMENTO E RIPRISTINO STRADA COMUNALE PER LA FRAZIONE DI IMARA DI SOTTO | € 23,646 |