CUP: G34E12000090001
SCUOLA COMUNALE LOC. VESCOVIO - REALIZZAZIONE IMPIANTO SOLARE FV E TERMICO
Download project
Funding monitored
€ 126,063.52
of which cohesion funds
€ 75,638.12
Given name | Amount |
---|---|
European Union | 37819.06 |
Revolving Fund (National co-financing) | 36395.06 |
Region | 1424.00 |
Municipality | 50425.40 |
- Economies:
- € 2,593.51
Payments monitored
€ 126,630.05
of which cohesion funds
€ 75,638.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2012 | 1003.43 | 1003.43 | 0 |
2013 | 125626.62 | 126630.05 | 100 |
State of progress
Completed
Expected start: 18/11/2012
Effective start: 07/11/2012
Expected end: 17/05/2013
Effective end: 17/05/2013
Entities
- Planning body
- REGIONE LAZIO
- Implementing body
- LAZIO INNOVA SPA
- Beneficiary
- LAZIO INNOVA SPA
- Executor
-
P. I. GIANCARLO BUCCINI
ENEL
ELETTROIMPIANTI UMBRA SRL
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- Programme
- ROP RCE ERDF LAZIO
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 75,638.12
- Payments on cohesion funds
- € 75,638.12
- Axis
- AMBIENTE E PREVENZIONE DEI RISCHI
- Operational objective
- Efficienza energetica e energia da fonti rinnovabili.