CUP: F23F08000010002
AMPLIAMENTO E COMPLETAMENTO AREA P.I.P. - COMUNE DI PIGNOLA
Download project
Funding monitored
€ 794,062.57
of which cohesion funds
€ 800,000.00
Given name | Amount |
---|---|
European Union | 424081.33 |
Revolving Fund (National co-financing) | 295984.99 |
Region | 73996.25 |
- Economies:
- € 5,937.43
Payments monitored
€ 794,062.57
of which cohesion funds
€ 794,062.57
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 126589.28 | 126589.28 | 15 |
2011 | 479397.42 | 605986.70 | 76 |
2012 | 74711.36 | 680698.06 | 85 |
2013 | 61369.93 | 742067.99 | 93 |
2014 | 0 | 742067.99 | 93 |
2015 | 51994.58 | 794062.57 | 100 |
State of progress
Completed
Expected start: 21/06/2010
Effective start: 21/06/2010
Expected end: 15/06/2011
Effective end: 03/08/2012
Type
- Infrastructure
- NUOVA REALIZZAZIONE
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE BASILICATA
- Implementing body
- COMUNE DI PIGNOLA
- Beneficiary
- COMUNE DI PIGNOLA
- Priority QSN
- Competitività dei sistemi produttivi e occupazione
- General objective QSN
- Promuovere processi sostenibili e inclusivi di innovazione e sviluppo imprenditoriale
- Specific objective QSN
- Migliorare l'efficacia dei servizi alle imprese
Programming area
- Programme
- ROP CONV ERDF BASILICATA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 800,000.00
- Payments on cohesion funds
- € 794,062.57
- Axis
- Competitività produttiva
- Operational objective
- Realizzazione di opere d'infrastrutturazione primaria e secondaria per la piena fruibilità di aree attrezzate per insediamenti produttivi già attivi.
Other projects in territory