CUP: F74C10000000005
IMPIANTO GEOTERMICO SEDE EX CONVENTO DEI TOLENTINI
Download project
Funding monitored
€ 222,108.57
of which cohesion funds
€ 155,834.81
Given name | Amount |
---|---|
European Union | 53062.05 |
Revolving Fund (National co-financing) | 55540.77 |
Region | 6925.47 |
Another public source | 106580.28 |
- Economies:
- € 40,306.52
Payments monitored
€ 222,108.55
of which cohesion funds
€ 115,528.28
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2009 | 5226.28 | 5226.28 | 2 |
2010 | 3484.19 | 8710.47 | 3 |
2011 | 83322.80 | 92033.27 | 41 |
2012 | 26953.66 | 118986.93 | 53 |
2013 | 103121.62 | 222108.55 | 99 |
State of progress
Completed
Expected start: 04/07/2011
Effective start: 25/11/2011
Expected end: 11/10/2012
Effective end: 26/06/2013
Type
- Infrastructure
- RESTAURO
Theme
- Energy
- Energia rinnovabile: idroelettrica, geotermale e altra
Territory
Entities
- Planning body
- REGIONE DEL VENETO
- Implementing body
- UNIVERSITA IUAV DI VENEZIA
- Beneficiary
- UNIVERSITA IUAV DI VENEZIA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Programme
- ROP RCE ERDF VENETO
- Axis
- Energia
- Operational objective
- Ridurre il consumo energetico e aumentare la produzione energetica da fonte rinnovabile.