CUP: G76H10000000009
REALIZZAZIONE DI UN PROGETTO PILOTA TRAMITE L'INSTALLAZIONE DI UN IMPIANTO DI ILLUMINAZIONE INNOVATIVO CON CORPI ILLUMINANTI A LED
Download project
Funding monitored
€ 200,689.04
of which cohesion funds
€ 200,888.00
Given name | Amount |
---|---|
European Union | 80275.62 |
Revolving Fund (National co-financing) | 84372.96 |
Development and Cohesion Fund | -83.57 |
Region | 36124.03 |
- Economies:
- € 198.96
Payments monitored
€ 200,689.04
of which cohesion funds
€ 200,689.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2010 | 61550.00 | 61550.00 | 30 |
2011 | 139139.04 | 200689.04 | 100 |
State of progress
Completed
Expected start: 01/09/2010
Effective start: 08/09/2010
Expected end: 31/01/2011
Effective end: 13/02/2011
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA
Theme
- Energy
- Efficienza dell'energia, cogenerazione, gestione dell'energia
Territory
Entities
- Planning body
- REGIONE AUTONOMA VALLE D'AOSTA
- Implementing body
- AUTOPORTO VALLE D'AOSTA SPA
- Beneficiary
- AUTOPORTO VALLE D'AOSTA SPA
- Priority QSN
- Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
- General objective QSN
- Promuovere le opportunità di sviluppo locale attraverso l'attivazione di filiere produttive collegate all'aumento della quota di energia prodotta da fonti rinnovabili e al risparmio energetico
- Specific objective QSN
- Diversificazione delle fonti energetiche e aumento dell'energia prodotta da fonti rinnovabili
Programming area
- Programme
- ROP RCE ERDF VALLE D'AOSTA
- European Regional Development Fund (ERDF)
- 2007-2013 EU Structural Funds
- Cohesion funds
- € 200,888.00
- Payments on cohesion funds
- € 200,689.04
- Axis
- Promozione dello sviluppo sostenibile
- Operational objective
- Promuovere lo sfruttamento efficiente di fonti di energia rinnovabili e l'efficienza energetica.