CUP: D23H14000040001
CARINI - ASI PALERMO - COMPLETAMENTO DEI COLLETTORI FOGNARI PREVISTI DAL PARF SECONDO STRALCIO (33407)
SUMMARY OF THE PROJECT
COMPLETAMENTO DEI COLLETTORI FOGNARI PREVISTI DAL PARF - 2° STRALCIO' NEL COMUNE DI CARINI
Download project
Funding monitored
€ 2,860,000.00
of which cohesion funds
€ 2,860,000.00
Given name | Amount |
---|---|
Resources released | 2860000.00 |
- Economies:
- € 91,707.00
Payments monitored
€ 2,093,244.45
of which cohesion funds
€ 1,986,066.65
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 21939.00 | 21939.00 | 0 |
2019 | 555551.76 | 577490.76 | 20 |
2020 | 519864.29 | 1097355.05 | 38 |
2021 | 345983.86 | 1443338.91 | 50 |
2022 | 429643.23 | 1872982.14 | 65 |
2023 | 220262.31 | 2093244.45 | 73 |
State of progress
Open
Expected start: 31/01/2014
Effective start: 25/02/2019
Expected end: 31/12/2015
Effective end: 09/09/2022
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMMISSARIO STRAORDINARIO UNICO DPCM DEL 07082023
Programming area
- Programme
- ROP ERDF SICILY
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 2,860,000.00
- Payments on cohesion funds
- € 1,986,066.65
- Axis
- TUTELARE L'AMBIENTE E PROMUOVERE L'USO EFFICIENTE DELLE RISO
- Specific objective
- MIGLIORAMENTO DEL SERVIZIO IDRICO INTEGRATO PER USI CIVILI E RIDUZIONE DELLE PERDITE DI RETE DI ACQUEDOTTO