Updated on 31/08/2024
Funding monitored € 699,774.68 of which cohesion funds € 699,774.68
Given name Amount
Another public source699774.68
Economies:
€ 3,225.32
Payments monitored € 699,774.68 of which cohesion funds € 699,774.68
Year Amount Cumulative amount Percentage on public financing
2010266783.12266783.1238
2011357360.35624143.4789
201275631.21699774.68100

State of progress

Completed
Expected start: 01/09/2010
Effective start: 30/11/2010
Expected end: 30/12/2011
Effective end: 18/12/2012

Type

Theme

Territory

Entities

Planning body
REGIONE SICILIANA
Beneficiary
REGIONE SICILIANA

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
PSC REGIONE SICILIANA
Policy Area
Ambiente e risorse naturali
Sector of intervention
Natura e biodiversita'

Other projects in territory

Same type of investment

PA AZIONI 1-2-4 PROGETTO FINALIZZATO AGLI INTERVENTI DI IMPLEMENTAZIONE DELLA SUPERFICIE BOSCATA, RICOSTITUZIONE DI BOSCHI PERCORSI DA INCENDIO, CONTRASTO DEL RISCHIO IDROGEOLOGICO ATTRAVERSO AZIONI DI PREVENZIONE E PROTEZIONE DELLE CAUSE DI DISSESTO E INTERVENTI DI PREVENZIONE SELVICOLTURALE TENDENTI AL CONTENIMENTO DEI DANNI CAUSATI DAL FUOCO SIA ATTRAVERSO LA DIMINUZIONE DEL MATERIALE COMBUSTIBILE CHE AL MIGLIORAMENTO DELLE CONDIZIONI DI RESISTENZA DEL SOPRASSUOLO BOSC € 996,000
SP N. 3 BIS DI TORRETTA: B° CAPACI - B° CAVALLARO - TORRETTA - B° BELLOLAMPO. LAVORI DI MANUTENZIONE STRAORDINARIA PER LA SISTEMAZIONE DEL PIANO VIABILE ED OPERE DI CORREDO € 989,442
LAVORI DI PREVENZIONE E CONTENIMENTO DELLA PROPAGAZIONE DEGLI INCENDI ATTRAVERSO IL RIPRISTINO DEI VIALI PARAFUOCO DA EFFETTUARSI CEI COMPLESSI BOSCATI DI MONTAGNA LONGA E MONTE PALMETO COMUNE DI CARINI, CASABOLI, SIGNORA, DAMMUSO, CERASA, AGLISOTTO COMUNE DI MONREALE, CANALINI COMUNE DI GIARDINELLO. € 987,937
COMUNE DI CARINI, LAVORI DI MANUTENZIONE STRAORDINARIA COMPRENDENTE L'ADEGUAMENTO ED IL COMPLETAMENTO DEGLI IMPIANTI E LA SISTEMAZIONE ESTERNA DELLA SCUOLA MEDIA S. CALDERONE € 525,766
PA AZIONI 1-2-4 PROGETTO FINALIZZATO AGLI INTERVENTI DI IMPLEMENTAZIONE DELLA SUPERFICIE BOSCATA, RICOSTITUZIONE DI BOSCHI PERCORSI DA INCENDIO, CONTRASTO DEL RISCHIO IDROGEOLOGICO ATTRAVERSO AZIONI DI PREVENZIONE E PROTEZIONE DELLE CAUSE DI DISSESTO E INTERVENTI DI PREVENZIONE SELVICOLTURALE TENDENTI AL CONTENIMENTO DEI DANNI CAUSATI DAL FUOCO SIA ATTRAVERSO LA DIMINUZIONE DEL MATERIALE COMBUSTIBILE CHE AL MIGLIORAMENTO DELLE CONDIZIONI DI RESISTENZA DEL SOPRASSUOLO BOSC € 450,000