CUP: B31B01000210005
Autostrada Messina-Palermo A20 - Impianti elettrici lotto N
SUMMARY OF THE PROJECT
Autostrada Messina-Palermo A20 - Impianti elettrici lotto N
Download project
Funding monitored
€ 14,387,316.07
of which cohesion funds
€ 14,387,316.07
Given name | Amount |
---|---|
Another public source | 14387316.07 |
- Economies:
- € 4,570,470.97
Payments monitored
€ 14,387,316.07
of which cohesion funds
€ 14,387,316.07
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2002 | 240217.69 | 240217.69 | 1 |
2003 | 204536.97 | 444754.66 | 3 |
2004 | 659700.00 | 1104454.66 | 7 |
2005 | 7252311.55 | 8356766.21 | 58 |
2006 | 5070638.44 | 13427404.65 | 93 |
2007 | 959911.42 | 14387316.07 | 100 |
State of progress
Completed
Expected start: 08/01/2004
Effective start: 05/08/2004
Expected end: 09/02/2010
Effective end: 29/06/2006
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- CONSORZIO PER LE AUTOSTRADE SICILIANE
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 14,387,316.07
- Payments on cohesion funds
- € 14,387,316.07
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale