CUP: C27H19002260001
CIMINNA. Riqualificazione della via Giovanni Falcone fino al Cimitero comunale (tratto finale da piazza Castello)
SUMMARY OF THE PROJECT
Rifacimento del manto stradale della via Giovani Falcone
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 580,000.00
of which cohesion funds
€ 580,000.00
Given name | Amount |
---|---|
Another public source | 580000.00 |
Payments monitored
€ 568,308.30
of which cohesion funds
€ 568,308.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 565395.35 | 565395.35 | 97 |
2024 | 2912.95 | 568308.30 | 97 |
State of progress
Completed
Expected start: 18/01/2023
Effective start: 13/02/2023
Expected end: 12/03/2024
Effective end: 04/08/2023
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI CIMINNA
- Executor
- COMUNE DI CIMINNA
Programming area
- Programme
- ACCORDO COESIONE SICILIA - FSC ANTICIPAZIONI
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 580,000.00
- Payments on cohesion funds
- € 568,308.30
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici