Updated on 31/12/2024
Funding monitored € 7,374,240.87 of which cohesion funds € 6,662,077.23
Given name Amount
Development and Cohesion Fund5476609.13
Status: other measures1897631.74
Economies:
€ 1,132,059.50
Payments monitored € 6,724,151.55 of which cohesion funds € 6,662,077.23
Year Amount Cumulative amount Percentage on public financing
2007566181.75566181.757
20081069638.981635820.7322
20091231170.742866991.4738
20103728660.306595651.7789
2011128499.786724151.5591

State of progress

Open
Expected start: 31/05/2007
Effective start: 11/05/2007
Expected end: 16/12/2009
Effective end: 17/12/2010

Type

Theme

Territory

Entities

Planning body
REGIONE SICILIANA
Implementing body
COMUNE DI AVOLA
Priority QSN
Energia e ambiente: uso sostenibile e efficiente delle risorse per lo sviluppo
General objective QSN
Garantire le condizioni di sostenibilità ambientale dello sviluppo e livelli adeguati di servizi ambientali per la popolazione e le imprese
Specific objective QSN
Accrescere la capacità di offerta, la qualità e l'efficienza del servizio idrico, e rafforzare la difesa del suolo e la prevenzione dei rischi naturali

Programming area

Programme
ROP CONV ERDF SICILY
European Regional Development Fund (ERDF)
2007-2013 EU Structural Funds
Cohesion funds
€ 6,662,077.23
Payments on cohesion funds
€ 6,662,077.23
Axis
Uso efficiente delle risorse naturali
Operational objective
Realizzare int.infrastrutt.prioritari lungo le fasi del ciclo delle acque,realizz.le infrastrutt.previste nella pianif.reg.le vigente,da assoc.al risp.idrico,riduz.di perdite,uso di fonti idriche alternat.,implem.strum.di pianificaz.sett.le.