CUP: G17H21026690006
S.P. 18 Nicosia - Agira dal Km 0+000 al Km 7+300 Bivio S.P. 85b - Manutenzione ordinaria piano viario
SUMMARY OF THE PROJECT
STRADA PROVINCIALE S.P.18 NICOSIA AGIRA DAL KM 0,00 AL KM 7+300 BIVIO S.P. 85B.*S.P. N. 18 - DAL KM 0,00 AL KM 7+300 BIVIO S.P. 85B.*MANUTENZIONE ORDINARIA PIANO VIARIO.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Download project
Funding monitored
€ 1,643,729.92
of which cohesion funds
€ 1,643,729.92
Given name | Amount |
---|---|
Another public source | 1643729.92 |
- Economies:
- € 551,270.08
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/06/2021
Effective start: 04/11/2021
Expected end: 30/05/2022
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI ENNA
Programming area
- Programme
- POC SICILIA
- None
- Piano d'Azione Coesione 2014/2020
- Cohesion funds
- € 1,643,729.92
- Payments on cohesion funds
- € 0.00
- CAP area axis
- CAP action line
- Interventi di riqualificazione della viabilità secondaria