CUP: C67H18002560001
INTERVENTO DI MESSA IN SICUREZZA DI TRATTI DELLE SEGUENTI STRADE COMUNALI ESTERNE AL CENTRO ABITATO - STRADA COMUNALE SPERLINGA - VILLADORO, STRADA COMUNALE MARRA (TRATTO), STRADA COMUNALE FERRIGNA - GURGAZZI COMUNE SPERLINGA
SUMMARY OF THE PROJECT
FONDO PER LO SVILUPPO E LA COESIONE 20142020: MESSA IN SICUREZZA DI STRADE COMUNALI DELLE AREE INTERNE CON MENO DI 2000 ABITANTI. RIFACIMENTO PAVIMENTAZIONE E REGIMAZIONE DELLE ACQUE METEORICHE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Download project
Funding monitored
€ 93,226.64
of which cohesion funds
€ 93,226.64
Given name | Amount |
---|---|
Another public source | 93226.64 |
Payments monitored
€ 77,668.19
of which cohesion funds
€ 77,668.19
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 77668.19 | 77668.19 | 83 |
State of progress
Open
Expected start: 01/07/2021
Effective start: 23/06/2022
Expected end: 20/08/2021
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI SPERLINGA
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 93,226.64
- Payments on cohesion funds
- € 77,668.19
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale