CUP: D78B20000920001
Troina (EN)_Consolidamento del versante sud ovest del quartiere Borgo e di contrada Candela e ripristino degli assi viari in frana.
SUMMARY OF THE PROJECT
CONSOLIDAMENTO DEL VERSANTE SUDOVEST DEL QUARTIERE BORGO E DI CONTRADA CANDELA E RIPRISTINO DEGLI ASSI VIARI IN FRANA.
Implementation indicator
Superficie oggetto di intervento
- Target
- 5,000 mq
- Achieved
- 0 mq
Download project
Funding monitored
€ 2,997,800.00
of which cohesion funds
€ 2,997,800.00
Given name | Amount |
---|---|
Another public source | 2997800.00 |
Payments monitored
€ 2,312,735.43
of which cohesion funds
€ 2,312,735.43
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 581231.16 | 581231.16 | 19 |
2022 | 854867.71 | 1436098.87 | 47 |
2023 | 436411.76 | 1872510.63 | 62 |
2024 | 440224.80 | 2312735.43 | 77 |
State of progress
Open
Expected start: 01/09/2021
Effective start: 09/08/2021
Expected end: 03/10/2022
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMMISSARIO DI GOVERNO CONTRO IL DISSESTO IDROGEOLOGICO NELLA REGIONE SICILIANA
- Executor
-
PRINCIPATO TROSSO LEONARDO
MAMMANA MICHELANGELO
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,997,800.00
- Payments on cohesion funds
- € 2,312,735.43
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico