CUP: H31F07000030001
Terza Sala Check In - Opere civili e impianti, Terza Sala Check In - Banchi Check In e altri arredi.
SUMMARY OF THE PROJECT
SICTBTA PA 06
Implementation indicator
Investimenti totali
- Target
- 2,414,237.48 euro
- Achieved
- 0 euro
Download project
Funding monitored
€ 1,608,140.15
of which cohesion funds
€ 1,608,140.15
Given name | Amount |
---|---|
Another public source | 1608140.15 |
- Economies:
- € 806,097.33
Payments monitored
€ 1,608,140.15
of which cohesion funds
€ 1,608,140.15
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2007 | 99424.50 | 99424.50 | 6 |
2008 | 9911.83 | 109336.33 | 6 |
2009 | 0 | 109336.33 | 6 |
2010 | 236100.00 | 345436.33 | 21 |
2011 | 584680.56 | 930116.89 | 57 |
2012 | 63732.53 | 993849.42 | 61 |
2013 | 101757.00 | 1095606.42 | 68 |
2014 | 0 | 1095606.42 | 68 |
2015 | 505813.56 | 1601419.98 | 99 |
2016 | 0 | 1601419.98 | 99 |
2017 | 6720.17 | 1608140.15 | 100 |
State of progress
Completed
Expected start: 12/01/2009
Effective start: 12/01/2009
Expected end: 29/06/2012
Effective end: 21/07/2015
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- GESAP S.P.A.
- Executor
- GESAP S.P.A.
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 1,608,140.15
- Payments on cohesion funds
- € 1,608,140.15
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto aereo