CUP: F12C05000090001
Itinerario Agrigento-Caltanissetta- A19- 2° tratto dal km 44 (Canicattì) al km 74+300 (A19) - Progettazione
SUMMARY OF THE PROJECT
SICISIS-2A-19/p
Download project
Funding monitored
€ 6,622,704.00
of which cohesion funds
€ 6,622,704.00
Given name | Amount |
---|---|
Another public source | 6622704.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 03/01/2005
Effective start: 05/07/2005
Expected end: 06/02/2009
Effective end: 28/01/2011
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS - SOCIETA' PER AZIONI
Programming area
- Programme
- PSC REGIONE SICILIANA
- Fondo Aree Sottoutilizzate 2000-2006
- 2000-2006 Underutilized Areas Fund
- Cohesion funds
- € 6,622,704.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale