CUP: C57H18001890002
SISTEMAZIONE MARCIAPIEDI ED INTERVENTI ALL'INTERNO DELLA VILLA COMUNALE IN ROMETTA MAREA
SUMMARY OF THE PROJECT
I LAVORI CONSISTONO NELLA SISTEMAZIONE DEI MARCIAPIEDI ED INTERVENTI ALL'INTERNO DELLA VILLA COMUNALE IN ROMETTA MAREA
Implementation indicator
Partecipanti disoccupati e lavoratori compresi quelli autonomi
- Target
- 15 persone
- Achieved
- 0 persone
Download project
Funding monitored
€ 88,183.26
of which cohesion funds
€ 88,183.26
Given name | Amount |
---|---|
Another public source | 88183.26 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 08/01/2020
Effective start: 26/01/2021
Expected end: 30/06/2021
Effective end: 27/07/2021
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI ROMETTA
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC SICILIA
- CAP area axis
- CAP action line
- Cantieri regionali di lavoro presso i Comuni della Sicilia (ex art. 15 comma 2 LR 3/16)