CUP: D67I18000130002
COMUNE - SOMMATINO - INTERVENTI DI RIQUALIFICAZIONE ED ADEGUAMENTO SCUOLA MEDIA STATALE LUCA PIGNATO RECUPERO E RISTRUTTURAZIONE DEL PLESSO DI VICOLO SETTEMBRINI
SUMMARY OF THE PROJECT
INTERVENTI DI RIQUALIFICAZIONE ED ADEGUAMENTO SCUOLA MEDIA STATALE LUCA PIGNATO - RECUPERO E RISTRUTTURAZIONE DEL PLESSO DI VICOLO SETTEMBRINI.
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 219 num
- Achieved
- 0 num
Download project
Funding monitored
€ 2,022,181.45
of which cohesion funds
€ 423,412.97
Given name | Amount |
---|---|
European Union | 1617745.16 |
Another public source | 404436.29 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/06/2020
Effective start: 12/04/2022
Expected end: 30/07/2021
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI SOMMATINO
Programming area
- Programme
- ROP ERDF SICILY
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 423,412.97
- Payments on cohesion funds
- € 0.00
- Axis
- Istruzione e Formazione
- Specific objective
- Aumento della propensione dei giovani a permanere nei contesti formativi e miglioramento della sicurezza e della fruibilità degli ambienti scolastici