CUP: F56G18000650002
MANUTENZIONE DEI CENTRI URBANI
SUMMARY OF THE PROJECT
DEMOLIZIONE PAVIMENTAZIONE E RIFACIMENTO DEI MARCIAPIEDI A DX E SX DI VARIE VIE
Implementation indicator
Partecipanti disoccupati e lavoratori compresi quelli autonomi
- Target
- 1 persone
- Achieved
- 0 persone
Download project
Funding monitored
€ 117,414.44
of which cohesion funds
€ 117,414.44
Given name | Amount |
---|---|
Another public source | 117414.44 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 20/11/2019
Effective start: 20/11/2019
Expected end: 28/02/2020
Effective end: 28/02/2020
Type
Theme
Territory
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI CASTELLANA SICULA
Programming area
- Programme
- POC SICILIA
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Cohesion funds
- € 117,414.44
- Payments on cohesion funds
- € 0.00
- CAP area axis
- CAP action line
- Cantieri regionali di lavoro presso i Comuni della Sicilia (ex art. 15 comma 2 LR 3/16)