LICODIA EUBEA LAVORI DI COMPLETAMENTO DEGLI INTERVENTI DI EFFICIENTAMENTO ENERGETICO E MESSA A NORMA DEGLI IMPIANTI DELL'INVOLUCRO EDILIZIO DELLA SCUOLA 'E. FERMI' DI VIA SAN PIETRO
SUMMARY OF THE PROJECT
LAVORI DI COMPLETAMENTO DEGLI INTERVENTI DI EFFICIENTAMENTO ENERGETICO E MESSA A NORMA DEGLI IMPIANTI DELL'INVOLUCRO EDILIZIO DELLA SCUOLA 'E. FERMI'
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 442 num
- Achieved
- 442 num
Download project
Funding monitored
€ 530,424.35
of which cohesion funds
€ 530,424.35
Given name | Amount |
---|---|
Another public source | 530424.35 |
Payments monitored
€ 94,121.22
of which cohesion funds
€ 94,121.22
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 94121.22 | 94121.22 | 17 |
State of progress
Open
Expected start: 02/09/2019
Effective start: 02/09/2019
Expected end: 22/09/2020
Effective end: 28/06/2021
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI LICODIA EUBEA
Programming area
- Programme
- ROP ERDF SICILY
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 530,424.35
- Payments on cohesion funds
- € 94,121.22
- Axis
- Istruzione e Formazione
- Specific objective
- Aumento della propensione dei giovani a permanere nei contesti formativi e miglioramento della sicurezza e della fruibilità degli ambienti scolastici