CUP: G88H18000080002
4.1.3 - COMUNE DI MILO (CT) -SERVIZIO ENERGETICO INTEGRATO RIFERITO ALLA GESTIONE DEL PATRIMONIO IMPIANTISTICO DEL COMUNE DI MILO CON RIQUALIFICAZIONE TECNOLOGICA ORIENTATA ALL'EFFICIENTAMENTO ENERGETICO
SUMMARY OF THE PROJECT
PARTENARIATI PUBBLICO PRIVATO PER LA REALIZZAZIONE DI OPERE DI EFFICIENTAMENTO ENERGETICO DEL COMPLETEZZA AZIONE PUBBLICA IMPLEMENTAZIONE DI SISTEMI DI SMART CITY E SUCCESSIVA GESTIONE DEL SERVIZIO
Implementation indicator
Punti illuminanti/luce
- Target
- 880 num
- Achieved
- 0 num
Download project
Funding monitored
€ 747,832.66
of which cohesion funds
€ 747,832.66
Given name | Amount |
---|---|
European Union | 293150.40 |
Another public source | 454682.26 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/01/2020
Effective start: 05/04/2023
Expected end: 30/06/2021
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI MILO
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili