CUP: G45I18000410008
COSTRUZIONE DI NUOVI TRATTI DI MARCIAPIEDI INDISPENSABILI PER LA SICUREZZA DELLA VIABILITA' VIA ORTOPOZZO, VIA LUIGI CAPUANA E VIA SALVATORE QUASIMODO
SUMMARY OF THE PROJECT
COSTRUZIONE DI NUOVI TRATTI DI MARCIAPIEDI INDISPENSABILI PER LA SICUREZZA DELLA VIABILITA' VIA ORTOPOZZO, VIA LUIGI CAPUANA E VIA SALVATORE QUASIMODO*VIA ORTOPOZZO, LUIGI CAPUANA E VIA SALVATORE QUASIMODO*COSTRUZIONI DI MARCIAPIEDI PER LA SICUREZZA DEI PEDONI
Implementation indicator
Partecipanti disoccupati e lavoratori compresi quelli autonomi
- Target
- 1 persone
- Achieved
- 1 persone
Download project
Funding monitored
€ 56,378.61
of which cohesion funds
€ 56,378.61
Given name | Amount |
---|---|
Another public source | 56378.61 |
- Economies:
- € 941.91
Payments monitored
€ 56,378.61
of which cohesion funds
€ 56,378.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 54278.48 | 54278.48 | 96 |
2021 | 1347.13 | 55625.61 | 98 |
2022 | 753.00 | 56378.61 | 100 |
State of progress
Completed
Expected start: 11/03/2020
Effective start: 08/07/2020
Expected end: 30/04/2020
Effective end: 22/10/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI RODI' MILICI
- Executor
- COMUNE DI RODI' MILICI
Programming area
- Programme
- POC SICILIA
- None
- Piano d'Azione Coesione 2014/2020
- Cohesion funds
- € 56,378.61
- Payments on cohesion funds
- € 56,378.61
- CAP area axis
- CAP action line
- Cantieri regionali di lavoro presso i Comuni della Sicilia (ex art. 15 comma 2 LR 3_16)