CUP: G17H18000700005
REALIZZAZIONE DI UN TRATTO DI MARCIAPIEDE LUNGO LA VIA ROSMARINO
SUMMARY OF THE PROJECT
SCAVO PER COLLOCAMENTO ORLATURA E FONDAZIONE MURO DI CONTENIMENTO, PAVIMENTAZIONE MARCIAPIEDE.
Implementation indicator
Partecipanti disoccupati e lavoratori compresi quelli autonomi
- Target
- 1 persone
- Achieved
- 0 persone
Funding monitored
€ 117,229.34
of which cohesion funds
€ 117,229.34
Given name | Amount |
---|---|
Another public source | 117229.34 |
Payments monitored
€ 29,706.73
of which cohesion funds
€ 29,706.73
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 22328.28 | 22328.28 | 19 |
2020 | 7378.45 | 29706.73 | 25 |
State of progress
Open
Expected start: 23/09/2019
Effective start: 01/07/2021
Expected end: 18/03/2020
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI TORRENOVA
Programming area
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Programme
- POC SICILIA
- CAP area axis
- CAP action line
- Cantieri regionali di lavoro presso i Comuni della Sicilia (ex art. 15 comma 2 LR 3/16)