CUP: J78H18000100008
4.1.3 PROGETTO DEFINITIVO DEGLI INTERVENTI DI ADEGUAMENTO DEGLI IMPIANTI DI PUBBLICA ILLUMINAZIONE RELAMPING CON TECNOLOGIA A LED TERRASINI
SUMMARY OF THE PROJECT
ADEGUAMENTO DEGLI IMPIANTI DI PUBBLICA ILLUMINAZIONE RELAMPING CON TECNOLOGIA A LED
Implementation indicator
Punti illuminanti/luce
- Target
- 943 num
- Achieved
- 0 num
Download project
Funding monitored
€ 746,907.62
of which cohesion funds
€ 746,907.62
Given name | Amount |
---|---|
European Union | 597526.10 |
Another public source | 149381.52 |
- Economies:
- € 251,092.38
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 03/11/2020
Effective start: 11/05/2023
Expected end: 30/06/2021
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI TERRASINI
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- ENERGIA SOSTENIBILE E QUALITA' DELLA VITA
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili
Other projects in territory
Same theme
REALIZZAZIONE DI UN IMPIANTO SOLARE TERMICO E FOTOVOLTAICO AL SERVIZIO DELLA PISCINA - COMUNE DI TERRASINI - PIST 26 - OP. 21 | € 391,460 |