CUP: I37H19001510002
LAVORI DI MANUTENZIONE STRAORDINARIA DELLA S.P. 195 (DAL KM 0+000 AL KM 1+520) E DELLA S.P. 196 (DAL KM 2+200 AL KM 5+783)
SUMMARY OF THE PROJECT
LAVORI DI MAUTENZIONE STRAORDINARIA DELLA SP 195 (DAL KM 0+000 AL KM 1+520) E DELLA SP 196 (DAL KM 2+200 AL KM 5+783)
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 5.20 km
- Achieved
- 5.20 km
Funding monitored
€ 499,489.97
of which cohesion funds
€ 499,489.97
Given name | Amount |
---|---|
Another public source | 499489.97 |
- Economies:
- € 230,443.03
Payments monitored
€ 489,466.74
of which cohesion funds
€ 489,466.74
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 232789.06 | 232789.06 | 46 |
2021 | 235085.25 | 467874.31 | 93 |
2022 | 7233.75 | 475108.06 | 95 |
2023 | 14358.68 | 489466.74 | 97 |
State of progress
Completed
Expected start: 10/12/2019
Effective start: 05/05/2020
Expected end: 10/04/2020
Effective end: 23/12/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI CALTANISSETTA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SICILIANA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale