CUP: J67B17000130001
LINEA FERROVIARIA CANICATTì-GELA-RAGUSA-SIRACUSA UPGRADING E MIGLIORAMENTO DELLA SICUREZZA DELL'INFRASTRUTTURA FERROVIARIA
SUMMARY OF THE PROJECT
LINEA FERROVIARIA CANICATTì-GELA-RAGUSA-SIRACUSA UPGRADING E MIGLIORAMENTO DELLA SICUREZZA DELL'INFRASTRUTTURA FERROVIARIA
Implementation indicator
Estensione dell'intervento in lunghezza
- Target
- 24,254 m
- Achieved
- 24,000 m
Download project
Funding monitored
€ 4,100,000.00
of which cohesion funds
€ 4,100,000.00
Given name | Amount |
---|---|
Another public source | 4100000.00 |
Payments monitored
€ 4,020,722.77
of which cohesion funds
€ 4,020,722.77
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 4020722.77 | 4020722.77 | 98 |
State of progress
Completed
Expected start: 06/12/2017
Effective start: 06/12/2017
Expected end: 25/02/2020
Effective end: 25/05/2019
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Programme
- ROP ERDF SICILY
- Axis
- Sistemi di Trasporto Sostenibili
- Specific objective
- POTENZIAMENTO FERROVIARIO REGIONALE, INTEGRAZIONE MODALE E MIGLIORAMENTO DEI COLLEGAMENTI MULTIMODALI CON I PRINCIPALI NODI URBANI, PRODUTTIVI E LOGISTICI E LA RETE CENTRALE, GLOBALE E LOCALE