CUP: F27H18002700002
lavori di manutenzione straordinaria nelle SS.PP. 78 e 89 - stralcio
SUMMARY OF THE PROJECT
rifacimento pavimentazioni stradali in conglomerato bituminoso, cunette in cls e segnaletica stradale orizzontale e verticale
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 10 km
- Achieved
- 10 km
Download project
Funding monitored
€ 461,705.90
of which cohesion funds
€ 461,705.90
Given name | Amount |
---|---|
Another public source | 461705.90 |
- Economies:
- € 188,294.10
Payments monitored
€ 446,107.72
of which cohesion funds
€ 446,107.72
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 380752.65 | 380752.65 | 82 |
2021 | 65355.07 | 446107.72 | 96 |
State of progress
Completed
Expected start: 05/10/2019
Effective start: 04/02/2020
Expected end: 02/04/2020
Effective end: 30/10/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI RAGUSA
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 461,705.90
- Payments on cohesion funds
- € 446,107.72
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale