CUP: B67H17000300001
lavori di manutenzione straordinaria lungo la S.P. Sinagra - Limari
SUMMARY OF THE PROJECT
risagomatura piano viabile, regimentazione acque meteoriche, consolidamento di scarpate, realizzazione barriere metalliche, gabbionate parapetti cunette espallette, segnaletica e lavori in economia.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 3.70 km
- Achieved
- 3.70 km
Download project
Funding monitored
€ 106,727.38
of which cohesion funds
€ 106,727.38
Given name | Amount |
---|---|
Another public source | 106727.38 |
- Economies:
- € 22,872.62
Payments monitored
€ 101,406.40
of which cohesion funds
€ 101,406.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 101406.40 | 101406.40 | 95 |
State of progress
Completed
Expected start: 10/10/2019
Effective start: 17/03/2021
Expected end: 26/01/2020
Effective end: 02/07/2021
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- PROVINCIA REGIONALE DI MESSINA
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 106,727.38
- Payments on cohesion funds
- € 101,406.40
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale