CUP: B97H15000590002
LAVORI DI ELIMINAZIONE DELLE CONDIZIONI DI PERICOLO PER IL RIPRISTINO DELLA REGOLARE TRANSITABILITÃ SULLA S.P.32 RIBERA - CIANCIANA
SUMMARY OF THE PROJECT
LAVORI DI ELIMINAZIONE DELLE CONDIZIONI DI PERICOLO PER IL RIPRISTINO DELLA REGOLARE TRANSITABILITÃ SULLA S.P.32 RIBERA - CIANCIANA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 10 km
- Achieved
- 10 km
Download project
Funding monitored
€ 1,000,000.27
of which cohesion funds
€ 1,000,000.27
Given name | Amount |
---|---|
Another public source | 1000000.27 |
Payments monitored
€ 706,427.04
of which cohesion funds
€ 706,427.04
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 3734.60 | 3734.60 | 0 |
2020 | 683781.17 | 687515.77 | 68 |
2021 | 18911.27 | 706427.04 | 70 |
State of progress
Open
Expected start: 03/01/2019
Effective start: 13/01/2020
Expected end: 03/03/2021
Effective end: 10/11/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI AGRIGENTO
Programming area
- Programme
- POC SICILIA
- 2014-2020 Cohesion Action Plan
- 2014-2020 Cohesion Action Plan
- Cohesion funds
- € 1,000,000.27
- Payments on cohesion funds
- € 706,427.04
- CAP area axis
- CAP action line