CUP: F27H18002550001
LAVORI DI SISTEMAZIONE DEI PARAPETTI DIVELTI LUNGO LA SS N. 120 DELL'ETNA E DELLE MADONIE IN TRATTI SALTUARI TRA IL KM 155+500 ED IL KM 215+627
SUMMARY OF THE PROJECT
L'INTERVENTO PREVEDE LA RIMOZIONE DEI PARAPETTI DANNEGGIATI IN MURATURA, E LA RISTRUTTURAZIONE DEGLI STESSI
Implementation indicators
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 23.95 km
- Achieved
- 23.95 km
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 23.95 km
- Achieved
- 23.95 km
km di strade ristrutturate (core indicator n° 16)
- Target
- 23.95 km
- Achieved
- 23.95 km
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 1,221,875.00
of which cohesion funds
€ 1,221,875.00
Given name | Amount |
---|---|
Another public source | 1221875.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 01/06/2019
Effective start: 29/07/2019
Expected end: 26/01/2020
Effective end: 09/03/2020
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,221,875.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale