CUP: J44H15000230002
COMUNE DI UCRIA - LAVORI DI MANUTENZIONE STRAORDINARIA, ADEGUAMENTO IMPIANTISTICO ED EFFICIENTAMENTO ENERGETICO, DELLA PALESTRA DEL PLESSO DI VIA SAN NICOLò
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA, ADEGUAMENTO IMPIANTISTICO EDEFFICIENTAMENTO ENERGETICO DELLA PALESTRA DI PERTINENZA DEL PLESSOSCOLASTICO COMUNALE
Implementation indicator
Capacità dell'infrastruttura per l'assistenza all'infanzia o l'istruzione sostenuta
- Target
- 44 num
- Achieved
- 44 num
Download project
Funding monitored
€ 387,908.79
of which cohesion funds
€ 387,908.79
Given name | Amount |
---|---|
Another public source | 387908.79 |
Payments monitored
€ 313,804.07
of which cohesion funds
€ 313,804.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 313804.07 | 313804.07 | 80 |
State of progress
Open
Expected start: 23/01/2018
Effective start: 22/02/2018
Expected end: 23/05/2018
Effective end: 03/07/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI UCRIA
Programming area
- Programme
- ROP ERDF SICILY
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 387,908.79
- Payments on cohesion funds
- € 313,804.07
- Axis
- Istruzione e Formazione
- Specific objective
- Aumento della propensione dei giovani a permanere nei contesti formativi e miglioramento della sicurezza e della fruibilità degli ambienti scolastici