CUP: B87H16001470002
LAVORI DI MANUTENZIONE STRAORDINARIA E MIGLIORAMENTO DELLA RETE VIARIA SECONDARIA PER UNA MAGGIORE ACCESSIBILITÃ ALLE AREE INTERNE E SUA MESSA IN SICUREZZA DORSALE S. BIAGIO PLATANI - CASTELTERMINI - STAZIONE ACQUAVIVA (S.S. 189 AG-PA)
SUMMARY OF THE PROJECT
RISAGOMATURA PIANO VIABILE, REALIZZAZIONE DI CUNETTE STRADALI E GABBIIONATE DI PROTEZIONE E CONTENIMENTO RIPE, MURI IN C.A., GUARD RAIL E SEGNALETICA STRADALE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 22.50 km
- Achieved
- 22.50 km
Download project
Funding monitored
€ 4,192,019.40
of which cohesion funds
€ 4,192,019.40
Given name | Amount |
---|---|
Another public source | 4192019.40 |
- Economies:
- € 976,980.60
Payments monitored
€ 4,044,934.84
of which cohesion funds
€ 4,044,934.84
96%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 13545.36 | 13545.36 | 0 |
2020 | 1185459.11 | 1199004.47 | 28 |
2021 | 2414494.38 | 3613498.85 | 86 |
2022 | 431435.99 | 4044934.84 | 96 |
State of progress
Settled
Expected start: 01/06/2018
Effective start: 17/07/2020
Expected end: 28/02/2020
Effective end: not available
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- LIBERO CONSORZIO COMUNALE DI AGRIGENTO
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 4,192,019.40
- Payments on cohesion funds
- € 4,044,934.84
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale