CUP: F57H17001060001
LAVORI DI RISANAMENTO DELLA SOVRASTRUTTURA STRADALE IN TRATTI SALTUARI LUNGO LA SS124 DAL KM 33+300 AL KM 106+650
SUMMARY OF THE PROJECT
LAVORI DI RISANAMENTO DELLA SOVRASTRUTTURA STRADALE IN TRATTI SALTUARI LUNGO LA SS124 DAL KM 33+300 AL KM 106+650
Implementation indicators
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 17.95 km
- Achieved
- 17.95 km
Lunghezza totale delle strade ricostruite o rinnovate di cui: TEN-T
- Target
- 17.95 km
- Achieved
- 17.95 km
km di strade ristrutturate (core indicator n° 16)
- Target
- 17.95 km
- Achieved
- 17.95 km
- Slide 1
- Slide 2
- Slide 3
Download project
Funding monitored
€ 742,989.07
of which cohesion funds
€ 742,989.07
Given name | Amount |
---|---|
Another public source | 742989.07 |
- Economies:
- € 257,010.93
Payments monitored
€ 603,836.64
of which cohesion funds
€ 603,836.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 568152.41 | 568152.41 | 76 |
2019 | 35684.23 | 603836.64 | 81 |
State of progress
Open
Expected start: 02/05/2018
Effective start: 02/05/2018
Expected end: 28/09/2018
Effective end: 02/05/2018
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC REGIONE SICILIANA
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale