CUP: E31E11000090002
COMUNE DI FICARRA - ADEGUAMENTO IMPIANTI E SISTEMAZIONE DEL CAMPO DI CALCIO IN LOCALITÃ NATOLI, DENOMINATO GAETANO MILIO
SUMMARY OF THE PROJECT
ADEGUAMENTO IMPIANTI E SISTEMAZIONE DEL CAMPO DI CALCIO IN LOCALITÃ NATOLI, DENOMINATO GAETANO MILIO
Download project
Funding monitored
€ 801,880.01
of which cohesion funds
€ 801,880.01
Given name | Amount |
---|---|
Another public source | 801880.01 |
- Economies:
- € 345,503.47
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 01/11/2017
Effective start: 05/02/2019
Expected end: 30/04/2018
Effective end: 28/12/2019
Entities
- Planning body
- REGIONE SICILIANA
- Beneficiary
- COMUNE DI FICARRA
Programming area
- Programme
- PSC REGIONE SICILIANA
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 801,880.01
- Payments on cohesion funds
- € 0.00
- Policy Area
- Riqualificazione Urbana
- Sector of intervention
- Edilizia e Spazzi Pubblici
Other projects in territory